You enter a resource’s cost per unit of duration in the Resource Table. If durations are measured in days, for example, you enter resource costs in cost per day. MacProject II then uses the resource duration to determine the cost for that resource on that task.
-- part contents for background part 27
----- text -----
Calculations
-- part contents for background part 28
----- text -----
Resource Costs
-- part contents for card part 29
----- text -----
cost per unit x resource duration
-- part contents for card part 30
----- text -----
1 of 2
-- part contents for background part 7
----- text -----
A resource’s cost for a task is:
The resource cost is assigned to the task and is associated with its Earliest Start date for the purposes of displaying costs in the Cash Flow Table.